At FarmLand Company, Lisa is preparing a commercial analysis of using drones for inventory check. The project is personally promoted by the general manager, but financial feasibility result shows that the project will not generate much return. FarmLand adopts a strict Stage-Gate product development process. The Gate is an important factor for the success of product development, because the Gate ensures: 在FarmLand公司,丽莎正在准备一份使用无人机清点库存数量的商业分析,该项目由总经理亲自推动,但财务可行性表明,该项目不会产生太多回报,FarmLand公司采用了严格的门径产品开发流程,关口是实现产品开发成功的重要因素,因为关口确保:
A. All projects are subject to be reviewed, but will continue to be developed 所有项目都需经过审核,但会一直继续开发下去
B. Only potentially successful projects will continue to be developed 只有可能成功的项目才会继续开发下去
C. All items are documented 所有项目都被记录在案
D. Projects supported by the general manager will be given priority按照总经理支持的项目将被优先考虑
上一题
下一题
收藏
点赞
评论
题目解析
题目评论(0)

P70 关口是产品开发流程中的一个确定节点,流程进行至此,需要做出有关项目的未来关键决策。 关口是必要的质量控制检查点,只有满足必须达到的标准才可以通过,其标准通常被设计为包括财务标准和定性标准在内的打分表等。

在FarmLand公司采用的严格的Stage-Gate产品开发流程中,"Gate"的存在是为了确保在产品开发过程的每个阶段,项目都经过严格的评审。其主要目的是筛选项目,以便资源能够集中于有潜力成功的项目上,因此这个流程的关键在于选择那些有最大发展潜力的项目继续进行开发。

基于Gate的定义和功能,正确的答案是:

**B: Only potentially successful projects will continue to be developed**

### 分析:

- **Stage-Gate流程概述**:
- **阶段(Stage)**:每一个阶段都是为了推进产品开发,包括概念开发、设计、测试等等。每个阶段都需要投入资源进行详细的工作。
- **关口(Gate)**:每个关口是一个决策点,在这里对项目进行评估和审查。项目团队需要向决策人或委员会展示项目的进展、财务可行性、市场潜力等信息。

- **Gate的目的**:
- **风险管理**:通过在每个阶段结束时进行评估,可以识别和规避潜在的风险,避免继续投资于低潜力或不可行的项目。
- **资源优化**:确保资源(时间、人力、资金)用于那些通过评估的、最有前途的项目。
- **提高成功率**:通过筛选,只允许高潜力的项目进入下一阶段,从而提高项目整体的成功率。

- **与选项的关系**:
- **选项 A**:不符合Stage-Gate的核心理念,它是为了筛选项目,而不是所有项目都继续。
- **选项 C**:虽然文档记录是项目管理的必要部分,但不是Gate的核心功能。
- **选项 D**:虽然总经理的支持可能会影响项目的优先级,但Stage-Gate流程的关键在于项目自身的可行性和潜力,而不是支持者的权力。

因此,正确答案是B,Stage-Gate流程主要是为了确保有限的资源投入到最有可能成功的项目中。