The company must choose between two new product investment opportunities with the same risks. The company now has an investment authority of USD 200 million, and the investment cost of Project X and Project Y each is USD 170 million. Based on financial projections, the net cash flow available (in millions of US dollars) is shown in the following table: Year1 Year2 Year3 Year4 Project X 40 70 60 30 Project Y 30 100 40 30 Which of the following statements is correct? 公司必须在两个具有相同风险的新产品投资机会中做出选择,公司现有2亿美元的投资可用权限,项目X和项目Y的投资费用均需1.7亿美元。 根据财务预测,可获得的净现金流(以百万美元计)如下表所示: Year1 Year2 Year3 Year4 Project X 40 70 60 30 Project Y 30 100 40 30 以下哪种说法是正确的?
A. Despite the same investment payback period, Project X is preferable 尽管投资回收期相同,项目X更可取
B. There is not enough data to choose between project X and project Y 没有是足够的数据在项目X和项目Y之间做出选择
C. Since the returns of the two projects are the same, both of which are USD 170 million, it is best for the company to wait to find other potential projects that can repay all USD 200 million. 出于两个项目的回报是相同的,均为1.7亿美元,公司最好等待找到其他可偿还全部2亿美元的潜在项目
D. These two projects have the same appeal 这两个项目具有同样的吸引力
上一题
下一题
收藏
点赞
评论
题目解析
题目评论(0)

分析题干,两个项目均投资1.7亿,都在公司投资权限内,投资回收期一致,净现值均为2亿,资金回收速度互有优势,无法做出选择。

要分析这两个项目,我们可以计算每个项目的净现值(NPV)或内部收益率(IRR),但在没有贴现率或其他具体财务指标的情况下,我们可以简单地比较其投资回收期。

项目X的净现金流为:
- 年1:40百万美元
- 年2:70百万美元
- 年3:60百万美元
- 年4:30百万美元

项目Y的净现金流为:
- 年1:30百万美元
- 年2:100百万美元
- 年3:40百万美元
- 年4:30百万美元

首先计算每个项目的投资回收期:

- 项目X在年1和年2合计110百万美元,年3再加60百万美元,总计170百万美元,因此在年3结束时收回全部投资。
- 项目Y在年1和年2合计130百万美元,年3再加40百万美元,总计170百万美元,因此同样在年3结束时收回全部投资。

因此,两个项目的投资回收期相同。接下来,我们可以比较年现金流的时间分布和总和:

- 项目X的前两年现金流较低,但较为稳定。
- 项目Y在第二年现金流较高,但第一年较低。

基于以上信息,选项A“尽管投资回收期相同,项目X更可取”可能是因为项目X的现金流较为稳定,并且在前期的现金流总额较高(年1和年2合计110百万美元),这可能会降低项目的初始风险。

因此,正确答案是A。